A1 and A3 CLAMP INSTALLATIONS -WHP

  Location Maari Field, New Zealand 
  Principal  MODEC/OMV
  Period June 2018 - August 2018

 

Air Diving and Subsea Project Management Services; 24- hour diving operations. Planning support for subsea input. Installations of the A1 (20 tonne) and A3 (8 tonne) clamps. A1 clamp installed in vertical position from approx. -4.5 to -16.5m. A3 installed in horizontal position.

No LTI’s, 10,608 minutes of BT, 19 personnel