A1 and A3 CLAMP INSTALLATIONS -WHP
A1 and A3 CLAMP INSTALLATIONS -WHP
Location
Maari Field, New Zealand
Principal
MODEC/OMV
Period
June 2018 - August 2018
Air Diving and Subsea Project Management Services; 24- hour diving operations. Planning support for subsea input. Installations of the A1 (20 tonne) and A3 (8 tonne) clamps. A1 clamp installed in vertical position from approx. -4.5 to -16.5m. A3 installed in horizontal position.
No LTI’s, 10,608 minutes of BT, 19 personnel